A team form the Mfantseman Municipal Assembly, met representatives of the Consultant Company, Sonam Consult Ltd, and representatives of the two contractors working on the above-mentioned project.

Upon the inspection, it was realized that, a drain is needed to be constructed somewhere at the middle part of the assess road to channel any possible waste water or rain water to join the main drains. This is so as to avoid water overflowing on the assess road.

The entire project was about 80 – 85 % completed.

Based on previously agreed timelines and adjustments made to the project duration, the entire project is expected to be completed by September 30, 2021.